The Creation of Phase II Church Building

The Family Life Center (FLC)

Construction contract signing, 02/29/2004

Ground breaking, 02/29/2004

Construction begin, 03/06 - 03/14/2004

Church bond sale, 03/13 - 03/20/2004

Drainage / piers / plumbing / slab preparation, 03/22/2004

Pour concrete slab, 03/30/2004

Grease trap & drainage / slab, 04/02/2004

Steel columns for partitions, 04/05/2004

Pour tilt wall concrete, 04/29/2004

Tilt walls installation, 04/02/2004

Parking lot / side walk / steel work, 05/20/2004

Roof work, 05/20/2004

Roof insulation installation, 05/28/2004

Roof work done, 06/03/2004

Plumbing / AC / electrical / partitions, 06/03 - 6/13/2004

Main entrance glass doors, 06/13/2004